Projects implemented between 2023 and 2028 are part of Great Lengths for the High Line, a $33 million campaign to ensure all 71 miles of the historic High Line Canal are preserved, protected and enhanced as a legacy greenway.. This campaign is leveraging public funding for a total investment of $100 million in the Canal over five years. For current projects underway, visit: highlinecanal.org/trail-improvements
*Great Lengths for the High Line includes private philanthropy, grants and foundations, and a $10M investment from Denver Water.
The Plan for the High Line Canal, created in 2019, lays out clear guidance for repurposing the Canal and recommends over 100 improvement projects. The following dashboard reflects the Conservancy and its partners’ progress as guided by The Plan over a 20-year span. To view the full Plan for the High Line Canal, visit: highlinecanal.org/plan.
Investment by character zone
COMPLETE
IN PROGRESS
FUTURE
COMPLETE
Pedestrian Bridges: Bannock St, Elati St
Accessible Access Points: Elati St Neighborhood Access
Enhanced Trailheads: Writers’ Vista Restrooms and Shelter
Tree Planting: Littleton
Stormwater Project: Mirabelle Stormwater Project
IN PROGRESS
Enhanced Trailheads: HLC Origin Trailhead
Trail Enhancements: HRMD Shared Trail
Underpasses: Santa Fe/Hwy 85 Underpass
Tree Planting: Douglas County, HRMD, Littleton
Pause Places: Little Willow Creek Gathering Area, Lee Gulch Flume Overlook
FUTURE
New Trailheads: Dry Creek Court Trailhead
Underpasses: S. Broadway, Mineral Ave.
Tree Planting: Douglas County, HRMD, Littleton
Pause Place: Ohlson Acres
COMPLETE
Pedestrian Bridges: Franklin St, deKoevend Parking Lot, Ice Arena, Hampden Underpass Connection
New Trailhead: Belleview Trailhead
Enhanced Trailheads: Milliken Park Restrooms, Orchard Trailhead Restrooms
Tree Planting: Centennial, Greenwood Village, Cherry Hills Village
Pause Place: Sumac Hill Farm Overlook
IN PROGRESS
Pedestrian Bridges: Quincy Farm
Tree Planting: Centennial, Greenwood Village, Cherry Hills Village
FUTURE
Tree Planting: Centennial, Greenwood Village, Cherry Hills Village
COMPLETE
Pedestrian Bridges: Holly and Eastman, Bible Park, Tower Road Trail Connection
New Trailhead: Quebec Way Trailhead
Underpasses: Hampden, Colorado, Parker
At-Grade Crossing Enhancements: Holly, Valentia, 2nd Ave
Tree Planting: Denver, unincorporated Arapahoe County
Stormwater Project: Eisenhower Park
Pause Place: Long’s Pine Grove
IN PROGRESS
Pedestrian Bridges: 8th Avenue
Canal Crossings: Granby Ditch, Laredo Elementary
Trail Enhancements: Denver Enhanced Trail Surface
Underpass: Colfax #1
At-Grade Crossing Enhancements: Yale, Quebec
Tree Planting: Denver, unincorporated Arapahoe County
Canal Improvement Zones: Goldsmith, Central Aurora, Laredo Highline
FUTURE
New Trailheads: Cherry Creek Confluence
Underpasses: Quebec, Havana, Sable
Tree Planting: Denver, unincorporated Arapahoe County
Canal Improvement Zones: Aurora City Center, DeLaney Farm
COMPLETE
New Trailhead: Triple Creek Trailhead
IN PROGRESS
Trail Enhancements: Colfax to I-70 Trail Completion
Canal Crossings: 17th Ave
Overpass: I-70
Canal Improvement Zones: Linear Park Loop
FUTURE
New Trailhead: 38th Avenue
Underpasses: Airport/Colfax #2
Canal Improvement Zones: Gateway to the Northeast